Fixed wire testing: a practical guide for occupied workplaces
Fixed wire testing can be coordinated around an occupied workplace when facilities teams and the testing contractor plan together. The priority is to give electricians safe access to the installation while helping everyone understand when particular equipment or areas will be unavailable.
Good preparation starts with three things: reliable circuit information, access to the right spaces and agreed isolation windows. Bringing these together before the visit helps the contractor assess the installation thoroughly and keeps building users informed.
Agree the scope and responsibilities first
Fixed wire testing examines the condition of the fixed electrical installation. Findings are recorded in an Electrical Installation Condition Report, usually called an EICR. It is different from portable appliance testing and does not replace separate maintenance arrangements for specialist systems.
Before booking, confirm which buildings, floors, distribution boards and associated circuits are included. In shared premises, clarify responsibility for landlord supplies, tenant installations and communal areas. Do not assume that an earlier report covered every part of the current installation.
J.Shaw Group’s EICR testing helps facilities teams understand the condition of their electrical installation and any action required.
Appoint a facilities contact who can arrange access, coordinate departments and authorise operational shutdowns. Provide a deputy for any evening or weekend attendance. Agree how questions about scope or unexpected findings will be escalated, especially if the person attending cannot approve changes.
Gather circuit records and flag anything uncertain

Send useful records to the contractor before the visit rather than leaving them to be discovered on arrival. These may include:
- The previous EICR and records of subsequent remedial work.
- Distribution board schedules and electrical drawings.
- Certificates for additions, alterations or recent refurbishment.
- A list of equipment that needs a controlled shutdown or specialist restart.
- Details of solar generation, batteries, generators and uninterruptible power supplies.
Explain where records may be incomplete. A board schedule might not reflect a recent office move, or a circuit label may describe a department that no longer occupies the space. Treat these as points for the electrician to verify, not as a basis for facilities staff to operate unfamiliar equipment.
Identify operational dependencies as well as circuit names. A supply labelled for an office could also serve network equipment used elsewhere. Ask department leads to flag shared services and equipment that must not lose power without preparation.
Do not remove covers or attempt circuit identification yourself. Leave electrical verification to competent electricians.
Arrange safe access throughout the workplace
The contractor may need access beyond the main switchroom, including local distribution boards, sockets, lighting points and equipment connections. Walk through the agreed areas beforehand and check that furniture, stock or stored materials will not obstruct access.
Confirm arrangements for keys, access cards, security escorts and restricted rooms. In tenanted buildings, obtain permission for individual units where needed. An accessible main board does not automatically mean every circuit can be inspected and tested.
Share site induction requirements, relevant risk information and any permit arrangements. This should include known asbestos information where relevant, vehicle movements, production hazards and restrictions around sensitive operations. Ask the contractor to confirm any access equipment or working area segregation required.
For production areas, involve someone who understands machine dependencies and restart procedures. Where testing identifies a need to alter supplies or controls, coordinated industrial electrical work can help address those requirements alongside the wider installation.
Build isolation windows around actual dependencies

Some inspection and testing requires circuits to be isolated. Agree these windows with the contractor rather than assuming testing can take place entirely with the power on. A window should allow for safe shutdown, isolation, testing, restoration and operational checks.
For each proposed isolation, record:
- The board or circuits involved and the areas expected to be affected.
- The equipment owner and person approving the shutdown.
- The agreed start time and planned restoration time.
- Shutdown, backup and restart requirements.
- The contact and decision process if the plan needs to change.
Consider servers, refrigeration, access control, lifts, process equipment and life safety systems. Their dependencies may extend beyond the area being tested. Involve specialist maintainers where necessary and agree suitable safeguards before affecting essential services.
A backup supply is not automatically safe to rely on or electrically separate from the work. Tell the contractor about every alternative source. Safe isolation, including controlling possible backfeeds and proving dead, must be managed by competent electricians.
Brief occupants and coordinate the testing day
Give staff and tenants a clear notice explaining which areas are affected, when power interruptions are planned and whom to contact with concerns. Ask equipment owners to complete agreed shutdowns and save work before the window begins. Avoid promising an exact restoration time unless it has been confirmed as realistic.
On the day, hold a short briefing with the contractor and facilities contact. Confirm access, the isolation sequence, any changes in occupancy and whether planned shutdowns are complete. Make sure reception and security know who is attending and which areas require access.
If a label is inaccurate or an unexpected supply is identified, pause the affected activity while the contractor establishes the position. Do not expand an isolation without checking its consequences and obtaining the necessary agreement.
Keep occupants away from electrical work areas. Only the responsible electricians should manage electrical isolation and authorise reenergisation under the agreed safe working arrangements.
Plan restoration and turn the report into action

Power restoration is not the same as operational readiness. Ask equipment owners to check their systems after the contractor confirms supplies can be used. Follow agreed restart sequences, particularly where machinery, controls or network equipment depend on other systems being available first.
Record any circuits that remain isolated, outstanding access requirements and further visits needed. Make sure the responsible people receive this information before the testing team leaves.
When the EICR arrives, review its extent, limitations, observations and recommended actions. A limitation records something that could not be inspected or tested; it is not confirmation that the excluded part is safe.
C1 observations indicate danger present and require immediate action. C2 observations identify potentially dangerous conditions requiring urgent remedial action. FI means further investigation is required without delay. C3 identifies an improvement recommendation. Agree responsibilities and next steps with the contractor, then retain the report and evidence of completed work with your electrical records.
- Confirm the testing scope and name a facilities contact.
- Share circuit records, known uncertainties and alternative supply details.
- Agree isolation windows with equipment owners and the contractor.
- Prepare access, occupant notices and controlled restart arrangements.
- Review the EICR and track any required action.
Frequently asked questions
Can people remain in the building during fixed wire testing?
Often, yes, provided safe working areas and suitable isolation arrangements can be maintained. The contractor should assess this with your facilities team. Some areas or activities may need to be temporarily unavailable.
Does the whole workplace need to lose power?
Not necessarily. Testing may be organised by board, circuit or area, depending on the installation. Some checks may require a wider shutdown. Confirm the proposed sequence after the contractor has reviewed the scope and supplies.
What if our distribution board schedules are incomplete?
Tell the contractor before attendance and share whatever records are available. Additional circuit identification may be needed. Do not guess which equipment a circuit supplies or rely on an uncertain label to authorise a shutdown.
How long should we allow for testing?
The time depends on the installation’s size, circuit numbers, accessibility and condition, as well as agreed shutdown arrangements. Share these details early so the contractor can propose a suitable programme and identify where flexibility is needed.
Prepare for your next workplace EICR
Talk to J.Shaw Group about your installation, access arrangements and operational priorities. We can help you plan fixed wire testing around safe access and agreed isolation windows.